Excavation is now complete in all 14 tunnels of the Sivok–Rangpo rail line to Sikkim

Indian Railways has finished excavating Tunnel No. 10, the 5.3-km longest tunnel on the 45-km Sivok–Rangpo new line, so excavation is complete in all 14 tunnels, the Ministry of Railways said. Lining, track laying and safety systems are still to come.

A misty green Himalayan valley with a river far below and a stone-lined tunnel entrance in the rocky hillside, with a gravel road leading to it

Indian Railways has finished excavating Tunnel No. 10 on the Sivok–Rangpo new line, the Ministry of Railways said, and with that excavation is now complete in all 14 tunnels of the project. At 5.3 km, it is the longest tunnel on the route. Crews worked on it from each end and from two side tunnels.

What is still to be done

Excavation is not the last step. Next come lining the tunnels, laying track and fitting safety systems, the ministry said.

The line

The 45-km broad-gauge line runs through Darjeeling and Kalimpong districts of West Bengal and Pakyong district of Sikkim, and joins the existing New Jalpaiguri–Alipurduar route at Sivok. The ministry says it will help move essential goods, give local businesses better access to markets and boost tourism. When it is finished, it will link Sikkim to the country’s rail network for the first time. The tunnels make up about 86 per cent of the route. Stations are planned at Sivok, Riyang, Melli and Rangpo, with an underground halt at Teesta Bazaar.